Coralius
5,800 cbm LNG Bunker-Vessel
for SIRIUS VEDER GAS AB, The Netherlands / Sweden
5,800 cbm LNG Bunker-Vessel
for SIRIUS VEDER GAS AB, The Netherlands / Sweden
| Project Data: | 2826 |
|---|---|
| Owner: | SIRIUS VEDER GAS AB, The Netherlands / Sweden |
| Shipyard: | Royal Bodewes, The Netherlands |
| Year of Completion: | 2017 |
| Classification: | BV |
| TGE's Scope: | Cargo handling system with cargo tanks, LNG fuel gas system |


| 5,800 cbm LNG Bunker-Vessel | |
|---|---|
| Length o.a. | 99.60 m |
| Beam: | 17.94 m |
| Draught (LNG): | 5.90 m |
| Speed: |
| Characteristics of gas plant: | |
|---|---|
| Capacity: | 5,800 m³ |
| Number of cargo tanks: | 2 (bilobe type) |
| Material of cargo tanks: | 9% Ni steel |
| Cargoes: | LNG |
| Design temperature / pressure: | -163°C / 4.5 bar g |
| Maximum cargo density: | 500 kg/m³ |
| Number of segregations: | 1 |
| Cargo manifolds: | 1 liquid line, 1 x 8” DIN 150 lbs flange 1 liquid branch, 1 x 8” DIN 150 lbs flange 1 vapour line, 1 x 6” DIN 150 lbs flange |
| Bunker manifolds: | 1 liquid line, 1 x 6” DIN 150 lbs flange 1 vapour line, 1 x 4” DIN 150 lbs flange |
| Loading- / Unloadingrate: | 840 m³/h |
| Deepwell pump | 4 x 210 m³/h at 210 mLC |
| BOG-handling & fuel gas system: | 2 x BOG compressors with intercoolers 2 x aftercoolers 2 x submerged fuel gas pumps 1 x forcing vaporiser 1 x fuel gas buffer tank 1 x fuel gas metering system |
| Cargo piping system: | Stainless steel, AISI 316L |
| Inertgas plant: | |
| Membrane system | Capacity: 100 Nm³/h at 3 vol. % O2 |